    Home»News»Govt Collects Shs13 Billion From Tolling Entebbe Expressway In Four Months
    News

    Govt Collects Shs13 Billion From Tolling Entebbe Expressway In Four Months

    Entebbe NewsBy Entebbe NewsJune 4, 2022No Comments4 Mins Read
    Facebook Twitter WhatsApp Telegram LinkedIn Email
    Entebbe expressway
    Entebbe expressway
    Share
    Facebook Twitter WhatsApp LinkedIn Email Telegram

    Uganda National Roads Authority-UNRA has collected a total of shillings 13 billion from tolling the Kampala-Entebbe expressway in the last four and a half months, the contractor Egis has revealed.

    Joy Nabasa, the Public Relations Manager of French Firm Egis, which maintains the road and collects the toll on behalf of UNRA, says that they collected the money between January 8, 2022, and May 24, 2022, when the exercise began.

    According to Nabasa, they also registered 2,206,558 from January to April, with a monthly average of 551,640 passages and 20,000 passages daily. She explains further that during the first four months, each of the three toll gates located in Mpala, Busega, and Kajjansi recorded an average of 6,664 passages daily.

    Allan Ssempebwa, the communications officer at UNRA, says the average of 20,000 passages made daily has surpassed the projected daily average of 13,000 passages. These include incoming and outgoing air passengers, taxi operators, visitors, and Entebbe residents. Ssempebwa says the number of passages has been increasing over the past four months from 480,234 passages in January to 574,629 in February, 594,124 in March, and 557,066 in April.

    free unlimited internet installation uganda by black knight africa

    Nabasa says May has so far recorded the highest number of passages at 630,000. This brings the total number of passages from January 8 to May 31 to 2,920,000. Ssempebwa says that the ever-increasing traffic on the road is an indicator that it is not a “white elephant as perceived by some sections of the public when the government announced plans to toll the expressway.

    “The more passages, the more money we will collect to repay the loan, operate and maintain the road,” he said. Motorists pay between Shillings 3,000 to 18,000 per trip on the expressway, which connects from Kampala Northern Bypass at Busega and joins the old Entebbe Road at Mpala. The collections will be used to repay the USD350 million loan government acquired from the Exim Bank of China to construct the 51.4-kilometer expressway.

    According to the loan agreement, the repayment schedule runs from July 21, 2019, to January 21, 2032. In the 13-year repayment period, the government plans to pay US$ 26.8 million (about UGX 95billion) every year. This means that the government should collect at least Shillings 7.8billion monthly to meet the loan obligation.

    However, some motorists led by lawyer Michael Aboneka want UNRA and Egis to install streetlights along the expressway. Aboneka has threatened to sue the government for failing to light the expressway and yet it collects over Shillings 2 billion monthly from the road toll. He wrote to the Minister of Works and Transport, General Katumba Wamala on March 23, 2022, about the lack of street lights.

    “As you are aware, the Kampala-Entebbe Expressway and the Kampala Northern By-pass are engulfed in darkness as they have no street lights. This is not only dangerous to motorists and road users but has also contributed to the insecurity and criminality on the two highways,” reads the letter.

    He asked Katumba’s “good office to urgently provide street lights on the two highways for the safety of Ugandans and all road users who painfully pay a road toll each time they use the Kampala-Entebbe Expressway.”

    Ssempebwa urges Aboneka and other road users to be patient, saying “we have procured over one thousand street lights to be installed on both sides of the road and hope to start installing them next month. We are only waiting for tax clearance from Uganda Revenue Authority for the lighting poles and lights.”

    Nabasa says Egis and UNRA are working round the clock to install streetlights on the road by end of this year. She adds that the lighting process involves designing the light set up, setting out and marking lighting locations, setting up electricity poles and substations, procurement, foundation, and erection of lighting poles, and connection of electricity to the poles.

    “The designs, location marking, and setting up of electricity poles and substations are complete while procurement of lighting poles is 50 percent. The rest of the activities are below 5percent because they can only be done once procurement is complete,” she said.

    -URN

    Digital Marketing Agency - Host256
    Digital Marketing Agency - Host256
    Entebbe expressway Kampala-Entebbe Expressway Uganda National Roads Authority UNRA
    Share. Facebook Twitter WhatsApp Telegram Email LinkedIn
    Entebbe News
    • Website
    • Facebook

    Related Posts

    NUP’s Kadondi sworn in as Makerere Guild President

    April 16, 2026

    MPs question army attire at MPs-elect training in Kyankwanzi

    April 15, 2026

    Okello collapses as witness linked him to Ggaba child killings

    April 15, 2026
    Leave A Reply Cancel Reply

    You must be logged in to post a comment.

    Entebbe News
    Facebook X (Twitter) Instagram WhatsApp
    © 2026 Entebbe News.

    Type above and press Enter to search. Press Esc to cancel.